Permitting Action Modification History

In Progress
U.S. Army Corps of Engineers determined that the application received on 07/29/2026 was determined to be complete on 08/03/2026.  This determination was made ahead of schedule due to the U.S. Army Corps of Engineers' early coordination with the applicant on the information needed for a complete application. They also coordinated early with the Lead Federal Agency, US Forest Service, on the need to confirm that the agency had sufficient information to ensure Section 7 of the ESA and Section 106 for NHPA compliance. The applicant submitted a PCN for nationwide permit verification., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-29-2026 07-29-2026 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-28-2026 08-03-2026 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 12-16-2027 12-16-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-29-2026 07-29-2026 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-28-2026 08-28-2026 --- No
Publication of Public Notice (Agency Action) 09-11-2026 09-11-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-16-2027 12-16-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-29-2026 07-29-2026 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-28-2026 08-28-2026 --- No
Publication of Public Notice (Agency Action) 09-11-2026 09-11-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-16-2027 12-16-2027 --- No