USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 07-29-2026 07-29-2026 --- Yes
Scoping (Agency Action) 07-29-2026 07-29-2026 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 11-16-2027 11-16-2027 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 11-16-2027 11-16-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 07-29-2026 07-29-2026 --- No
Scoping (Agency Action) 07-29-2026 07-29-2026 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 11-16-2027 11-16-2027 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 11-16-2027 11-16-2027 --- No