Permitting Action Modification History

Complete
Agency issued final decision ahead of FAST-41 Dashboard schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 02-19-2026 02-19-2026 --- Yes
Application deemed complete (Agency Action) 07-21-2026 09-18-2026 --- Yes
Final decision/agency action (Agency Action) 08-20-2026 10-16-2026 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 02-19-2026 02-19-2026 --- Yes
Application deemed complete (Agency Action) 07-21-2026 09-18-2026 --- Yes
Final decision/agency action (Agency Action) 08-20-2026 10-19-2026 --- No
Planned
While the Project Sponsor has been responsive to requests for the required information, the applications provided by the May 22, 2026 milestone were not complete. The milestones are dependent on all outstanding application materials being submitted by the applicant, so the milestones are being shifted by 60 days to allow time to review the complete applications once received., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 02-19-2026 02-19-2026 --- Yes
Application deemed complete (Agency Action) 07-21-2026 09-18-2026 --- No
Final decision/agency action (Agency Action) 08-20-2026 10-19-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 02-19-2026 02-19-2026 --- Yes
Application deemed complete (Agency Action) 07-21-2026 07-21-2026 --- No
Final decision/agency action (Agency Action) 08-20-2026 08-20-2026 --- No