Permitting Action Modification History
Modifications on 08/05/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| UIC permit application submitted | 12-23-2025 | 12-23-2025 | Yes |
| UIC permit application complete | 04-15-2026 | 04-15-2026 | Yes |
| Issuance of final UIC permit decision | 08-31-2026 | 12-17-2026 | No |
Modifications on 04/30/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| UIC permit application submitted | 12-23-2025 | 12-23-2025 | Yes |
| UIC permit application complete | 04-15-2026 | 04-15-2026 | Yes |
| Issuance of final UIC permit decision | 08-31-2026 | 08-31-2026 | No |
Modifications on 04/22/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| UIC permit application submitted | 07-30-2025 | 07-30-2025 | Yes |
| UIC permit application complete | 04-15-2026 | 04-15-2026 | Yes |
| Issuance of final UIC permit decision | 08-31-2026 | 08-31-2026 | No |