Permitting Action Modification History
Modifications on 08/10/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 03-04-2026 | 03-04-2026 | --- | Yes |
| NOAA determines ESA Consultation Package is Complete - Informal (Agency Action) | 04-03-2026 | 04-03-2026 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 08-17-2026 | 08-07-2026 | --- | Yes |
Modifications on 04/07/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 03-04-2026 | 03-04-2026 | --- | Yes |
| NOAA determines ESA Consultation Package is Complete - Informal (Agency Action) | 04-03-2026 | 04-03-2026 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 08-17-2026 | 08-17-2026 | --- | No |