Permitting Action Modification History
Modifications on 10/28/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 06-01-2026 | 09-15-2027 | --- | No |
| Final decision/agency action (Agency Action) | 11-15-2027 | 11-15-2027 | --- | No |
Modifications on 04/29/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 06-01-2026 | 09-15-2027 | --- | No |
| Final decision/agency action (Agency Action) | 11-15-2027 | 11-12-2027 | --- | No |
Modifications on 03/20/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 06-01-2026 | 06-01-2026 | --- | No |
| Application deemed complete (Agency Action) | 10-01-2027 | 10-01-2027 | --- | No |
| Final decision/agency action (Agency Action) | 11-15-2027 | 11-15-2027 | --- | No |