Permitting Action Modification History
Modifications on 07/14/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 07-15-2026 | 07-14-2026 | --- | Yes |
| Application deemed complete (Agency Action) | 01-05-2028 | 01-05-2028 | --- | No |
| Final decision/agency action (Agency Action) | 01-31-2028 | 01-31-2028 | --- | No |
Modifications on 03/20/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 07-15-2026 | 07-15-2026 | --- | No |
| Application deemed complete (Agency Action) | 01-05-2028 | 01-05-2028 | --- | No |
| Final decision/agency action (Agency Action) | 01-31-2028 | 01-31-2028 | --- | No |