Permitting Action Modification History
Modifications on 03/20/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Submittal of draft initial Plan of Operations (Applicant Action) | 01-06-2025 | 01-06-2025 | --- | Yes |
| Submittal of complete initial Plan of Operations (Applicant Action) | 02-25-2025 | 02-25-2025 | --- | Yes |
| Acceptance of complete initial Plan of Operations (Agency Action) | 11-24-2025 | 11-24-2025 | --- | Yes |
| Submittal of final Plan of Operations and financial assurance (Applicant Action) | 01-12-2028 | 01-12-2028 | --- | No |
| Approval of final Plan of Operations (Agency Action) | 03-15-2028 | 03-15-2028 | --- | No |