Permitting Action Modification History

Complete
USACE issued Section 10 verification two months ahead of schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 02-23-2026 02-23-2026 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 03-25-2026 02-23-2026 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 06-11-2026 04-09-2026 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 02-23-2026 02-23-2026 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 03-25-2026 02-23-2026 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 06-11-2026 06-11-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 02-23-2026 02-23-2026 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 03-25-2026 03-25-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 06-11-2026 06-11-2026 --- No