USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
SHPO and tribal concurrence achieved by 3/22/26.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-02-2026 01-02-2026 --- Yes
Section 106 consultation concluded (Agency Action) 03-22-2026 03-22-2026 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-02-2026 01-02-2026 --- Yes
Section 106 consultation concluded (Agency Action) 03-22-2026 03-22-2026 --- No