Permitting Action Modification History
Modifications on 06/10/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Agency Action) | 06-05-2025 | 06-05-2025 | --- | Yes |
| Completed application received (Agency Action) | 06-11-2026 | 06-09-2026 | --- | Yes |
| Final decision/agency action (Agency Action) | 09-29-2028 | 09-29-2028 | --- | No |
Modifications on 02/06/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Agency Action) | 06-05-2025 | 06-05-2025 | --- | Yes |
| Completed application received (Agency Action) | 06-11-2026 | 06-11-2026 | --- | No |
| Final decision/agency action (Agency Action) | 09-29-2028 | 09-29-2028 | --- | No |
Modifications on 02/06/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Agency Action) | 06-05-2025 | 06-05-2025 | --- | Yes |
| Completed application received (Agency Action) | 06-11-2026 | 06-11-2026 | --- | No |
| Final decision/agency action (Agency Action) | 09-29-2028 | 09-29-2028 | --- | No |