Permitting Action Modification History
Modifications on 05/01/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| EFH Consultation Request Submitted – EFH Assessment (Agency Action) | 03-30-2026 | 03-30-2026 | --- | No |
| NOAA determines EFH Assessment is Complete (Agency Action) | 04-29-2026 | 04-29-2026 | --- | No |
| NOAA Issues any EFH Conservation Recommendations (Agency Action) | 07-29-2026 | 07-29-2026 | --- | No |
Modifications on 04/30/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| EFH Consultation Request Submitted – EFH Assessment (Agency Action) | 03-30-2026 | 03-30-2026 | --- | No |
| NOAA determines EFH Assessment is Complete (Agency Action) | 04-29-2026 | 04-29-2026 | --- | Yes |
| NOAA Issues any EFH Conservation Recommendations (Agency Action) | 07-29-2026 | 07-29-2026 | --- | No |
Modifications on 03/11/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| EFH Consultation Request Submitted – EFH Assessment (Agency Action) | 03-30-2026 | 03-30-2026 | --- | No |
| NOAA determines EFH Assessment is Complete (Agency Action) | 04-29-2026 | 04-29-2026 | --- | No |
| NOAA Issues any EFH Conservation Recommendations (Agency Action) | 07-29-2026 | 07-29-2026 | --- | No |
Modifications on 01/30/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| EFH Consultation Request Submitted – EFH Assessment (Agency Action) | 03-30-2026 | 03-30-2026 | --- | No |
| NOAA determines EFH Assessment is Complete (Agency Action) | 04-29-2026 | 04-29-2026 | --- | No |
| NOAA Issues any EFH Conservation Recommendations (Agency Action) | 07-29-2026 | 07-29-2026 | --- | No |