Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-30-2026 03-27-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 04-29-2026 04-29-2026 --- Yes
ESA Consultation Concludes (Agency Action) 09-11-2026 05-20-2026 --- Yes
Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-30-2026 03-27-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 04-29-2026 04-28-2026 --- No
ESA Consultation Concludes (Agency Action) 09-11-2026 05-20-2026 --- Yes
Complete
ESA Consultation with USFWS was completed earlier than originally scheduled.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-30-2026 03-27-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 04-29-2026 04-28-2026 --- Yes
ESA Consultation Concludes (Agency Action) 09-11-2026 05-20-2026 --- Yes
In Progress
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) was completed early.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-30-2026 03-27-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 04-29-2026 04-28-2026 --- Yes
ESA Consultation Concludes (Agency Action) 09-11-2026 09-11-2026 --- No
Planned
ESA Consultation Request Package was submitted one day ahead of targeted date.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-30-2026 03-27-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 04-29-2026 04-29-2026 --- No
ESA Consultation Concludes (Agency Action) 09-11-2026 09-11-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-30-2026 03-30-2026 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 04-29-2026 04-29-2026 --- No
ESA Consultation Concludes (Agency Action) 09-11-2026 09-11-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-30-2026 03-30-2026 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 04-29-2026 04-29-2026 --- No
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 04-29-2026 04-29-2026 --- No
ESA Consultation Concludes (Agency Action) 09-11-2026 09-11-2026 --- No