USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-30-2026 03-27-2026 --- Yes
NOAA determines ESA Consultation Package is Complete - Informal (Agency Action) 04-29-2026 04-29-2026 --- Yes
ESA Consultation Concludes (Agency Action) 05-29-2026 05-29-2026 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-30-2026 03-27-2026 --- Yes
NOAA determines ESA Consultation Package is Complete - Informal (Agency Action) 04-29-2026 04-29-2026 --- Yes
ESA Consultation Concludes (Agency Action) 05-29-2026 05-29-2026 --- No
Planned
ESA Consultation Package was submitted one day ahead of schedule.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-30-2026 03-27-2026 --- Yes
NOAA determines ESA Consultation Package is Complete - Informal (Agency Action) 04-29-2026 04-29-2026 --- No
ESA Consultation Concludes (Agency Action) 05-29-2026 05-29-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 03-30-2026 03-30-2026 --- No
NOAA determines ESA Consultation Package is Complete - Informal (Agency Action) 04-29-2026 04-29-2026 --- No
ESA Consultation Concludes (Agency Action) 05-29-2026 05-29-2026 --- No