Permitting Action Modification History
Modifications on 06/23/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 02-28-2026 | 02-27-2026 | --- | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 03-30-2026 | 03-11-2026 | --- | Yes |
| Final Verification/Permit Decision Rendered (Agency Action) | 09-18-2026 | 06-22-2026 | --- | Yes |
Modifications on 03/11/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 02-28-2026 | 02-27-2026 | --- | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 03-30-2026 | 03-11-2026 | --- | Yes |
| Final Verification/Permit Decision Rendered (Agency Action) | 09-18-2026 | 09-18-2026 | --- | No |
Modifications on 03/02/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 02-28-2026 | 02-27-2026 | --- | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 03-30-2026 | 03-30-2026 | --- | No |
| Final Verification/Permit Decision Rendered (Agency Action) | 09-18-2026 | 09-18-2026 | --- | No |
Modifications on 01/30/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 02-28-2026 | 02-28-2026 | --- | No |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 03-30-2026 | 03-30-2026 | --- | No |
| Final Verification/Permit Decision Rendered (Agency Action) | 09-18-2026 | 09-18-2026 | --- | No |