USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
Due to the Section 106 being completed early, NMFS ESA completed as scheduled, and USFWS ESA completed early and informally, this allowed USACE to complete its evaluation ahead of schedule., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 02-28-2026 02-27-2026 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 03-30-2026 03-11-2026 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 09-18-2026 06-22-2026 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 02-28-2026 02-27-2026 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 03-30-2026 03-11-2026 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 09-18-2026 09-18-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 02-28-2026 02-27-2026 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 03-30-2026 03-30-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-18-2026 09-18-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 02-28-2026 02-28-2026 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 03-30-2026 03-30-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-18-2026 09-18-2026 --- No