Permitting Action Modification History
Modifications on 03/02/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-02-2026 | 02-02-2026 | --- | Yes |
| Application deemed complete (Agency Action) | 02-27-2026 | 02-27-2026 | --- | Yes |
| Final decision/agency action (Agency Action) | 09-11-2026 | 09-11-2026 | --- | No |
Modifications on 02/03/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-02-2026 | 02-02-2026 | --- | Yes |
| Application deemed complete (Agency Action) | 02-27-2026 | 02-27-2026 | --- | No |
| Final decision/agency action (Agency Action) | 09-11-2026 | 09-11-2026 | --- | No |
Modifications on 01/30/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-02-2026 | 02-02-2026 | --- | No |
| Application deemed complete (Agency Action) | 02-27-2026 | 02-27-2026 | --- | No |
| Final decision/agency action (Agency Action) | 09-11-2026 | 09-11-2026 | --- | No |