Planned
Initial 90% Submittal, 90% Completeness Determination, 90% Decision, Initial 100% Submittal, 100% Completeness Determination, 100% Complete Application, and Issuance of Decision all updated per revised schedule from Current Hydro by email dated 9-Oct-2026., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 05-15-2026 05-17-2026 --- Yes
Completeness Determination (Agency Action) 02-11-2027 03-31-2027 --- No
Complete application submitted (Applicant Action) 02-16-2027 04-05-2027 --- No
Issuance of Decision (Agency Action) 05-15-2027 06-04-2027 --- No
Planned
USACE received an automated DoD SAFE notification that the design zip file had been sent Saturday morning, May 16, 2026, at 12:24 a.m. (ET), However, the passphrase needed from Current Hydro to download the encrypted zip file was sent Sunday morning, May 17, 2026, at 12:54 a.m. (ET).  On May 17, 2026, the RC Byrd Hydropower Section 408 Design Submission was successfully downloaded and disseminated to the USACE team for review.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 05-15-2026 05-17-2026 --- Yes
Completeness Determination (Agency Action) 02-11-2027 02-11-2027 --- No
Complete application submitted (Applicant Action) 02-16-2027 02-16-2027 --- No
Issuance of Decision (Agency Action) 05-15-2027 05-15-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 05-15-2026 05-15-2026 --- No
Completeness Determination (Agency Action) 02-11-2027 02-11-2027 --- No
Complete application submitted (Applicant Action) 02-16-2027 02-16-2027 --- No
Issuance of Decision (Agency Action) 05-15-2027 05-15-2027 --- No