Permitting Action Modification History
Modifications on 10/29/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 09-29-2026 | 09-28-2026 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Informal (Agency Action) | 10-29-2026 | 10-29-2026 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 02-11-2027 | 11-30-2026 | --- | No |
Modifications on 09/28/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 09-29-2026 | 09-28-2026 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 10-29-2026 | 10-29-2026 | --- | No |
| ESA Consultation Concludes (Agency Action) | 02-11-2027 | 02-11-2027 | --- | No |
Modifications on 01/30/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 09-29-2026 | 09-29-2026 | --- | No |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 10-29-2026 | 10-29-2026 | --- | No |
| ESA Consultation Concludes (Agency Action) | 02-11-2027 | 02-11-2027 | --- | No |