Permitting Action Modification History
Modifications on 09/28/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Determination to prepare an Environmental Assessment (EA) (Agency Action) | 01-14-2026 | 01-14-2026 | --- | Yes |
| Issuance of a Final EA (Agency Action) | 09-29-2026 | 09-28-2026 | --- | Yes |
| EA Process Concluded (Agency Action) | 09-29-2026 | 09-28-2026 | --- | Yes |
Modifications on 01/30/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Determination to prepare an Environmental Assessment (EA) (Agency Action) | 01-14-2026 | 01-14-2026 | --- | Yes |
| Issuance of a Final EA (Agency Action) | 09-29-2026 | 09-29-2026 | --- | No |
| EA Process Concluded (Agency Action) | 09-29-2026 | 09-29-2026 | --- | No |