Permitting Action Modification History

Complete
Completed 2/10/2026, earlier than target date 3/9/2026 , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 01-21-2026 01-21-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 02-05-2026 02-05-2026 --- Yes
ESA Consultation Concludes (Agency Action) 03-09-2026 02-10-2026 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 01-21-2026 01-21-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 02-05-2026 02-05-2026 --- Yes
ESA Consultation Concludes (Agency Action) 03-09-2026 03-09-2026 --- No