Permitting Action Modification History

Complete
The Fish and Wildlife Service's Golden Eagle Disturbance Take Permit and associated Categorical Exclusion were finalized and signed ahead of schedule issuing GSV a 5-year disturbance take permit for up to 10 incidents of golden eagle disturbance over the permit term.  This milestone was achieved early - one day ahead of schedule.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 12-22-2025 12-22-2025 --- Yes
Application deemed complete (Agency Action) 04-20-2026 04-17-2026 --- Yes
Final decision/agency action (Agency Action) 06-18-2026 06-16-2026 --- Yes
In Progress
Milestone was met early 4/17, basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 12-22-2025 12-22-2025 --- Yes
Application deemed complete (Agency Action) 04-20-2026 04-17-2026 --- Yes
Final decision/agency action (Agency Action) 06-18-2026 06-18-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 12-22-2025 12-22-2025 --- Yes
Application deemed complete (Agency Action) 04-20-2026 04-20-2026 --- No
Final decision/agency action (Agency Action) 06-18-2026 06-18-2026 --- No