Permitting Action Modification History

Complete
FWS completed BO early, basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 10-28-2025 10-28-2025 --- Yes
FWS Requests Additional Information (Agency Action) 12-05-2025 12-05-2025 --- Yes
Lead Agency Responds to Additional Information Request (Agency Action) 12-31-2025 12-31-2025 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 01-30-2026 01-23-2026 --- Yes
ESA Consultation Concludes (Agency Action) 06-15-2026 06-05-2026 --- Yes
In Progress
The USFWS was able to determine the formal consultation package was complete 1 week early, which has a cascading effect on other actions and milestones. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 10-28-2025 10-28-2025 --- Yes
FWS Requests Additional Information (Agency Action) 12-05-2025 12-05-2025 --- Yes
Lead Agency Responds to Additional Information Request (Agency Action) 12-31-2025 12-31-2025 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 01-30-2026 01-23-2026 --- Yes
ESA Consultation Concludes (Agency Action) 06-15-2026 06-07-2026 --- No
In Progress
ESA consultation package is marked complete ahead of schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 10-28-2025 10-28-2025 --- Yes
FWS Requests Additional Information (Agency Action) 12-05-2025 12-05-2025 --- Yes
Lead Agency Responds to Additional Information Request (Agency Action) 12-31-2025 12-31-2025 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 01-30-2026 01-23-2026 --- Yes
ESA Consultation Concludes (Agency Action) 06-15-2026 06-15-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 10-28-2025 10-28-2025 --- Yes
FWS Requests Additional Information (Agency Action) 12-05-2025 12-05-2025 --- Yes
Lead Agency Responds to Additional Information Request (Agency Action) 12-31-2025 12-31-2025 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 01-30-2026 01-30-2026 --- No
ESA Consultation Concludes (Agency Action) 06-15-2026 06-15-2026 --- No