Permitting Action Modification History
Modifications on 08/14/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 08-13-2025 | 08-13-2025 | --- | Yes |
| Scoping (Agency Action) | 09-18-2025 | 09-18-2025 | --- | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 08-14-2026 | 08-07-2026 | 08-14-2026 | Yes |
| Issuance of Lead Agency Record of Decision (Agency Action) | 08-14-2026 | 08-07-2026 | 08-14-2026 | Yes |
Modifications on 02/04/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 08-13-2025 | 08-13-2025 | --- | Yes |
| Scoping (Agency Action) | 09-18-2025 | 09-18-2025 | --- | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 08-14-2026 | 08-07-2026 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 08-14-2026 | 08-07-2026 | --- | No |
Modifications on 01/02/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 08-13-2025 | 08-13-2025 | --- | Yes |
| Scoping (Agency Action) | 09-18-2025 | 09-18-2025 | --- | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 08-14-2026 | 08-14-2026 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 08-14-2026 | 08-14-2026 | --- | No |