Permitting Action Modification History

Complete
The Bureau of Land Management (BLM) missed the August 7, 2026, milestone to publish the Final Environmental Impact Statement (FEIS) in order to facilitate additional administrative review. The review of the project required enhanced coordination that affected the timeline for this project by one week, including the Mine Plan of Operations milestones., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial Mine Plan of Operations received (Applicant Action) 11-13-2020 11-13-2020 --- Yes
Completeness determination for Mine Plan of Operations (Agency Action) 05-07-2025 05-07-2025 --- Yes
Issuance of decision for Mine Plan of Operations (Agency Action) 08-14-2026 08-07-2026 08-14-2026 Yes
Financial assurance received (Applicant Action) 10-13-2026 08-08-2026 08-14-2026 Yes
In Progress
The USFWS was able to determine the formal consultation package was complete 1 week early, which has a cascading effect on other actions and milestones. The Project Sponsor determined that they would be able to provide the Financial assurance on 8/8/26. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial Mine Plan of Operations received (Applicant Action) 11-13-2020 11-13-2020 --- Yes
Completeness determination for Mine Plan of Operations (Agency Action) 05-07-2025 05-07-2025 --- Yes
Issuance of decision for Mine Plan of Operations (Agency Action) 08-14-2026 08-07-2026 --- No
Financial assurance received (Applicant Action) 10-13-2026 08-08-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial Mine Plan of Operations received (Applicant Action) 11-13-2020 11-13-2020 --- Yes
Completeness determination for Mine Plan of Operations (Agency Action) 05-07-2025 05-07-2025 --- Yes
Issuance of decision for Mine Plan of Operations (Agency Action) 08-14-2026 08-14-2026 --- No
Financial assurance received (Applicant Action) 10-13-2026 10-13-2026 --- No