Permitting Action Modification History
Modifications on 06/24/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-26-2026 | 04-28-2026 | --- | Yes |
| NOAA Requests Additional Information (Agency Action) | 07-27-2026 | 05-06-2026 | --- | Yes |
| Lead Agency Responds to Additional Information Request (Agency Action) | 08-10-2026 | 05-20-2026 | --- | Yes |
| NOAA determines ESA Consultation Package is Complete - Informal (Agency Action) | 05-20-2026 | 05-20-2026 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 01-07-2027 | 06-22-2026 | --- | Yes |
Modifications on 05/19/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-26-2026 | 04-28-2026 | --- | Yes |
| NOAA Requests Additional Information (Agency Action) | 07-27-2026 | 05-06-2026 | --- | Yes |
| Lead Agency Responds to Additional Information Request (Agency Action) | 08-10-2026 | 08-10-2026 | --- | No |
| NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) | 08-25-2026 | 08-25-2026 | --- | No |
| ESA Consultation Concludes (Agency Action) | 01-07-2027 | 01-07-2027 | --- | No |
Modifications on 03/02/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-26-2026 | 06-26-2026 | --- | No |
| NOAA Requests Additional Information (Agency Action) | 07-27-2026 | 07-27-2026 | --- | No |
| Lead Agency Responds to Additional Information Request (Agency Action) | 08-10-2026 | 08-10-2026 | --- | No |
| NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) | 08-25-2026 | 08-25-2026 | --- | No |
| ESA Consultation Concludes (Agency Action) | 01-07-2027 | 01-07-2027 | --- | No |