Permitting Action Modification History

Complete
USFWS received a complete BA from the LA and project sponsor. Through interagency coordination and communication USFWS was able to prioritize the FAST-41 project and will continue to do so when feasible., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-26-2026 06-26-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-27-2026 07-13-2026 --- Yes
ESA Consultation Concludes (Agency Action) 11-09-2026 07-31-2026 --- Yes
In Progress
The USFWS is ahead of schedule due to early coordinator efforts and receiving a complete BA from the lead agency and project sponsor. USFWS continues to prioritize FAST-41 projects when feasible., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-26-2026 06-26-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-27-2026 07-13-2026 --- Yes
ESA Consultation Concludes (Agency Action) 11-09-2026 07-31-2026 --- No
In Progress
USFWS is ahead of schedule due to early coordination efforts. USFWS will continue to prioritize FAST-41 projects as is feasible., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-26-2026 06-26-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-27-2026 07-13-2026 --- Yes
ESA Consultation Concludes (Agency Action) 11-09-2026 11-09-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-26-2026 06-26-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-27-2026 07-27-2026 --- No
ESA Consultation Concludes (Agency Action) 11-09-2026 11-09-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-26-2026 06-26-2026 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-27-2026 07-27-2026 --- No
ESA Consultation Concludes (Agency Action) 11-09-2026 11-09-2026 --- No