Permitting Action Modification History
Modifications on 08/03/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-26-2026 | 06-26-2026 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 07-27-2026 | 06-29-2026 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 11-09-2026 | 07-31-2026 | --- | Yes |
Modifications on 07/13/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-26-2026 | 06-26-2026 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 07-27-2026 | 06-29-2026 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 11-09-2026 | 07-31-2026 | --- | No |
Modifications on 07/02/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-26-2026 | 06-26-2026 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 07-27-2026 | 06-29-2026 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 11-09-2026 | 11-09-2026 | --- | No |
Modifications on 06/26/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-26-2026 | 06-26-2026 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 07-27-2026 | 07-27-2026 | --- | No |
| ESA Consultation Concludes (Agency Action) | 11-09-2026 | 11-09-2026 | --- | No |
Modifications on 01/02/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-26-2026 | 06-26-2026 | --- | No |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 07-27-2026 | 07-27-2026 | --- | No |
| ESA Consultation Concludes (Agency Action) | 11-09-2026 | 11-09-2026 | --- | No |