Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-26-2026 06-26-2026 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-09-2026 06-29-2026 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 12-07-2026 08-31-2026 --- Yes
In Progress
USACE Section 10/404 milestone for MS Crossing moved from December 7, 2026 to August 31, 2026.Justification: USACE continues to prioritize FAST‑41 projects, whenever feasible. USACE collaborated closely with the applicant to ensure submission of a complete application, aligning with FERC's FEIS, thereby enabling more efficient and timely processing of the PCN., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-26-2026 06-26-2026 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-09-2026 06-29-2026 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 12-07-2026 08-31-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-26-2026 06-26-2026 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-09-2026 08-09-2026 --- No
Publication of Public Notice (Agency Action) 08-24-2026 08-24-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-07-2026 12-07-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 06-26-2026 06-26-2026 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-09-2026 08-09-2026 --- No
Publication of Public Notice (Agency Action) 08-24-2026 08-24-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-07-2026 12-07-2026 --- No