Permitting Action Modification History

Complete
The Georgia, Mississippi, and Alabama SHPOs concurred that the project would not adversely affect historic properties. In the final EIS, Commission staff agreed with this conclusion., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-30-2025 06-30-2025 --- Yes
Section 106 consultation concluded (Agency Action) 07-31-2026 06-26-2026 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-30-2025 06-30-2025 --- Yes
Section 106 consultation concluded (Agency Action) 07-31-2026 07-31-2026 --- No