Modifications on 06/29/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 06-30-2025 | 06-30-2025 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 07-31-2026 | 06-26-2026 | --- | Yes |
Modifications on 01/02/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 06-30-2025 | 06-30-2025 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 07-31-2026 | 07-31-2026 | --- | No |