Permitting Action Modification History
Modifications on 01/27/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent (NOI) or Notice to prepare a Supplemental EIS (Agency Action) | 01-26-2026 | 01-26-2026 | --- | Yes |
| Official Notice of Availability of a Final Supplemental EIS published in the FR (Agency Action) | 04-23-2027 | 04-23-2027 | --- | No |
| Supplemental EIS process concluded (Agency Action) | 05-28-2027 | 05-28-2027 | --- | No |
Modifications on 12/23/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent (NOI) or Notice to prepare a Supplemental EIS (Agency Action) | 01-26-2026 | 01-26-2026 | --- | No |
| Official Notice of Availability of a Final Supplemental EIS published in the FR (Agency Action) | 04-23-2027 | 04-23-2027 | --- | No |
| Supplemental EIS process concluded (Agency Action) | 05-28-2027 | 05-28-2027 | --- | No |