Permitting Action Modification History
Modifications on 08/24/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 06-15-2026 | 08-21-2026 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 09-01-2026 | 01-11-2027 | --- | No |
Modifications on 06/25/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 06-15-2026 | 08-25-2026 | --- | No |
| Section 106 consultation concluded (Agency Action) | 09-01-2026 | 01-11-2027 | --- | No |
Modifications on 05/15/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 06-15-2026 | 07-13-2026 | --- | No |
| Section 106 consultation concluded (Agency Action) | 09-01-2026 | 09-01-2026 | --- | No |
Modifications on 12/19/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 06-15-2026 | 06-15-2026 | --- | No |
| Section 106 consultation concluded (Agency Action) | 09-01-2026 | 09-01-2026 | --- | No |