Permitting Action Modification History
Modifications on 08/12/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Determination to prepare an Environmental Assessment (EA) (Agency Action) | 04-07-2026 | 08-11-2026 | --- | Yes |
| Issuance of a Final EA (Agency Action) | 09-01-2026 | 01-11-2027 | --- | No |
| EA Process Concluded (Agency Action) | 12-18-2026 | 03-11-2027 | --- | No |
Modifications on 06/25/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Determination to prepare an Environmental Assessment (EA) (Agency Action) | 04-07-2026 | 08-11-2026 | --- | No |
| Issuance of a Final EA (Agency Action) | 09-01-2026 | 01-11-2027 | --- | No |
| EA Process Concluded (Agency Action) | 12-18-2026 | 03-11-2027 | --- | No |
Modifications on 04/08/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Determination to prepare an Environmental Assessment (EA) (Agency Action) | 04-07-2026 | 04-07-2026 | --- | Yes |
| Issuance of a Final EA (Agency Action) | 09-01-2026 | 09-01-2026 | --- | No |
| EA Process Concluded (Agency Action) | 12-18-2026 | 12-18-2026 | --- | No |
Modifications on 12/19/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Determination to prepare an Environmental Assessment (EA) (Agency Action) | 04-07-2026 | 04-07-2026 | --- | No |
| Issuance of a Final EA (Agency Action) | 09-01-2026 | 09-01-2026 | --- | No |
| EA Process Concluded (Agency Action) | 12-18-2026 | 12-18-2026 | --- | No |