Permitting Action Modification History
Modifications on 06/12/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-17-2026 | 02-17-2026 | --- | Yes |
| Application deemed complete (Agency Action) | 04-07-2026 | 04-07-2026 | --- | Yes |
| Final decision/agency action (Agency Action) | 01-15-2027 | 01-15-2027 | --- | No |
Modifications on 04/08/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-17-2026 | 02-17-2026 | --- | Yes |
| Application deemed complete (Agency Action) | 04-07-2026 | 04-07-2026 | --- | Yes |
| Final decision/agency action (Agency Action) | 01-15-2027 | 01-15-2027 | --- | No |
Modifications on 02/18/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-17-2026 | 02-17-2026 | --- | Yes |
| Application deemed complete (Agency Action) | 04-07-2026 | 04-07-2026 | --- | No |
| Final decision/agency action (Agency Action) | 01-15-2027 | 01-15-2027 | --- | No |
Modifications on 12/19/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 02-17-2026 | 02-17-2026 | --- | No |
| Application deemed complete (Agency Action) | 04-07-2026 | 04-07-2026 | --- | No |
| Final decision/agency action (Agency Action) | 01-15-2027 | 01-15-2027 | --- | No |