Permitting Action Modification History

In Progress
The NEPA is now anticipated to be an EA and the Mine Plan of Operations timeline has been changed to reflect this change., basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Initial Mine Plan of Operations received (Applicant Action) 02-03-2026 02-03-2026 Yes
Completeness determination for Mine Plan of Operations (Agency Action) 03-04-2026 03-04-2026 Yes
Issuance of decision for Mine Plan of Operations (Agency Action) 11-13-2028 04-30-2027 No
Financial assurance received (Applicant Action) 05-13-2028 05-14-2027 No
In Progress
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Initial Mine Plan of Operations received (Applicant Action) 02-03-2026 02-03-2026 Yes
Completeness determination for Mine Plan of Operations (Agency Action) 03-04-2026 03-04-2026 Yes
Issuance of decision for Mine Plan of Operations (Agency Action) 11-13-2028 11-13-2028 No
Financial assurance received (Applicant Action) 05-13-2028 05-13-2028 No
Planned
This POO timeline was submitted by the applicant. This timeline includes the line item of Financial assurance received. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Initial Mine Plan of Operations received (Applicant Action) 02-03-2026 02-03-2026 Yes
Completeness determination for Mine Plan of Operations (Agency Action) 03-04-2026 03-04-2026 No
Issuance of decision for Mine Plan of Operations (Agency Action) 11-13-2028 11-13-2028 No
Financial assurance received (Applicant Action) 05-13-2028 05-13-2028 No