Permitting Action Modification History

Planned
USACE must adjust the alternative completion dates for the ESA action. USACE has been working with the project sponsor to complete information needed to make an ESA effects determination on listed species and initiate Section 7 consultation under the ESA. However, the project sponsor is still identifying locations and plans for on-site and off-site compensatory mitigation. The sponsor must provide a complete description of the proposed action to initiate consultation, including information and details on all on-site and off-site permittee-responsible stream and wetland compensatory mitigation sites and their proposed plans. The applicant intends to submit this information by the end of January 2027. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-01-2026 07-31-2026 02-17-2027 No
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 09-01-2026 09-01-2026 03-17-2027 No
ESA Consultation Concludes (Agency Action) 01-14-2027 01-14-2027 07-30-2027 No
Planned
USACE, as the lead federal agency, was unable to provide an effects determination and Biological Assessment (BA) to the USFWS.  The project sponsor is still performing required species surveys in the month of August 2026.  Once the surveys are completed, a BA and effects determination will be provided to USFWS., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-01-2026 07-31-2026 10-23-2026 No
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 09-01-2026 09-01-2026 11-23-2026 No
ESA Consultation Concludes (Agency Action) 01-14-2027 01-14-2027 04-07-2027 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-01-2026 07-31-2026 --- No
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 09-01-2026 09-01-2026 --- No
ESA Consultation Concludes (Agency Action) 01-14-2027 01-14-2027 --- No
Planned
USFWS coordinated with USACE for Dashboard entry and this milestones was completed early., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-01-2026 07-31-2026 --- Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 09-01-2026 09-01-2026 --- No
ESA Consultation Concludes (Agency Action) 01-14-2027 01-14-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-01-2026 08-01-2026 --- No
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 09-01-2026 09-01-2026 --- No
ESA Consultation Concludes (Agency Action) 01-14-2027 01-14-2027 --- No