Permitting Action Modification History
Modifications on 07/31/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Determination to prepare an Environmental Assessment (EA) (Agency Action) | 08-01-2026 | 07-31-2026 | --- | Yes |
| Issuance of a Final EA (Agency Action) | 08-01-2027 | 08-01-2027 | --- | No |
| EA Process Concluded (Agency Action) | 08-01-2027 | 08-01-2027 | --- | No |
Modifications on 12/09/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Determination to prepare an Environmental Assessment (EA) (Agency Action) | 08-01-2026 | 08-01-2026 | --- | No |
| Issuance of a Final EA (Agency Action) | 08-01-2027 | 08-01-2027 | --- | No |
| EA Process Concluded (Agency Action) | 08-01-2027 | 08-01-2027 | --- | No |