Permitting Action Modification History
Modifications on 07/31/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 06-01-2026 | 06-01-2026 | --- | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 07-15-2026 | 07-15-2026 | --- | Yes |
| Publication of Public Notice (Agency Action) | 08-01-2026 | 07-31-2026 | --- | Yes |
| Final Verification/Permit Decision Rendered (Agency Action) | 08-01-2027 | 08-01-2027 | --- | No |
Modifications on 07/16/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 06-01-2026 | 06-01-2026 | --- | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 07-15-2026 | 07-15-2026 | --- | Yes |
| Publication of Public Notice (Agency Action) | 08-01-2026 | 08-01-2026 | --- | No |
| Final Verification/Permit Decision Rendered (Agency Action) | 08-01-2027 | 08-01-2027 | --- | No |
Modifications on 06/03/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 06-01-2026 | 06-01-2026 | --- | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 07-15-2026 | 07-15-2026 | --- | No |
| Publication of Public Notice (Agency Action) | 08-01-2026 | 08-01-2026 | --- | No |
| Final Verification/Permit Decision Rendered (Agency Action) | 08-01-2027 | 08-01-2027 | --- | No |
Modifications on 12/09/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 06-01-2026 | 06-01-2026 | --- | No |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 07-15-2026 | 07-15-2026 | --- | No |
| Publication of Public Notice (Agency Action) | 08-01-2026 | 08-01-2026 | --- | No |
| Final Verification/Permit Decision Rendered (Agency Action) | 08-01-2027 | 08-01-2027 | --- | No |