Permitting Action Modification History

Complete
Corps completed their assessment and issued the permit 4 days ahead of schedule. The permit was sent to the applicant on 21 SEP 26., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-24-2026 07-24-2026 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-07-2026 08-07-2026 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 12-05-2026 09-21-2026 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-24-2026 07-24-2026 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-07-2026 08-07-2026 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 12-05-2026 09-24-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-24-2026 07-24-2026 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-07-2026 08-07-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-05-2026 09-24-2026 --- No
Planned
Approved JD determined project could be reviewed as a Nation-Wide permit., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-24-2026 07-24-2026 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-07-2026 08-07-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-05-2026 09-24-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-24-2026 07-24-2026 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-07-2026 08-07-2026 --- No
Publication of Public Notice (Agency Action) 08-07-2026 08-07-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-05-2026 12-05-2026 --- No