Permitting Action Modification History
Modifications on 09/11/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 11-14-2025 | 11-14-2025 | --- | Yes |
| Scoping (Agency Action) | 11-14-2025 | 11-14-2025 | --- | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 04-01-2026 | 04-01-2026 | --- | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 07-24-2026 | 07-24-2026 | --- | Yes |
| Issuance of Lead Agency Record of Decision (Agency Action) | 09-17-2026 | 09-10-2026 | --- | Yes |
Modifications on 07/24/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 11-14-2025 | 11-14-2025 | --- | Yes |
| Scoping (Agency Action) | 11-14-2025 | 11-14-2025 | --- | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 04-01-2026 | 04-01-2026 | --- | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 07-24-2026 | 07-24-2026 | --- | Yes |
| Issuance of Lead Agency Record of Decision (Agency Action) | 09-17-2026 | 09-17-2026 | --- | No |
Modifications on 04/01/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 11-14-2025 | 11-14-2025 | --- | Yes |
| Scoping (Agency Action) | 11-14-2025 | 11-14-2025 | --- | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 04-01-2026 | 04-01-2026 | --- | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 07-24-2026 | 07-24-2026 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 09-17-2026 | 09-17-2026 | --- | No |
Modifications on 12/04/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 11-14-2025 | 11-14-2025 | --- | Yes |
| Scoping (Agency Action) | 11-14-2025 | 11-14-2025 | --- | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 04-01-2026 | 04-01-2026 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 07-24-2026 | 07-24-2026 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 09-17-2026 | 09-17-2026 | --- | No |