Permitting Action Modification History
Modifications on 09/30/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 04-06-2026 | 12-16-2026 | No |
| Section 106 consultation concluded (Agency Action) | 11-06-2026 | 03-17-2027 | No |
Modifications on 08/04/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 04-06-2026 | 11-13-2026 | No |
| Section 106 consultation concluded (Agency Action) | 11-06-2026 | 02-12-2027 | No |
Modifications on 12/02/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | --- | 04-06-2026 | No |
| Section 106 consultation concluded (Agency Action) | --- | 11-06-2026 | No |