Permitting Action Modification History
Modifications on 09/30/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 09-30-2026 | 12-16-2026 | No |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 11-02-2026 | 01-15-2027 | No |
| ESA Consultation Concludes (Agency Action) | 02-12-2027 | 05-31-2027 | No |
Modifications on 08/04/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 09-30-2026 | 10-01-2026 | No |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 11-02-2026 | 11-02-2026 | No |
| ESA Consultation Concludes (Agency Action) | 02-12-2027 | 03-17-2027 | No |
Modifications on 12/02/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | --- | 09-30-2026 | No |
| ESA Consultation Concludes (Agency Action) | --- | 02-12-2027 | No |