USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
The Fish and Wildlife Service's Golden Eagle Disturbance Take Permit and associated Categorical Exclusion were finalized and signed ahead of schedule, issuing GSV a 5-year disturbance take permit for up to 10 incidents of golden eagle disturbance over the permit term. This is a result of close coordination and collaboration. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 12-22-2025 12-22-2025 --- Yes
Application deemed complete (Agency Action) 04-20-2026 04-17-2026 --- Yes
Final decision/agency action (Agency Action) 06-26-2026 06-16-2026 --- Yes
In Progress
Milestone completed early., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 12-22-2025 12-22-2025 --- Yes
Application deemed complete (Agency Action) 04-20-2026 04-17-2026 --- Yes
Final decision/agency action (Agency Action) 06-26-2026 06-26-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 12-22-2025 12-22-2025 --- Yes
Application deemed complete (Agency Action) 04-20-2026 04-20-2026 --- No
Final decision/agency action (Agency Action) 06-26-2026 06-26-2026 --- No