Permitting Action Modification History
Modifications on 12/11/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-30-2025 | 06-30-2025 | --- | Yes |
| FWS Requests Additional Information (Agency Action) | 07-07-2025 | 07-07-2025 | --- | Yes |
| Lead Agency Responds to Additional Information Request (Agency Action) | 09-22-2025 | 09-22-2025 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 09-30-2025 | 09-30-2025 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 09-29-2025 | 09-29-2025 | --- | Yes |
Modifications on 12/03/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-30-2025 | 06-30-2025 | --- | Yes |
| FWS Requests Additional Information (Agency Action) | 07-07-2025 | 07-07-2025 | --- | Yes |
| Lead Agency Responds to Additional Information Request (Agency Action) | 09-22-2025 | 09-22-2025 | --- | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 09-30-2025 | 09-30-2025 | --- | Yes |
| ESA Consultation Concludes (Agency Action) | 09-29-2025 | 09-29-2025 | --- | Yes |