Permitting Action Modification History

Complete
Internal review and concurrence process for the licensing decision was completed ahead of time, thus contributing to early completion of the licensing decision., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 03-04-2024 03-04-2024 --- Yes
Acceptance review complete (Agency Action) 06-24-2024 06-24-2024 --- Yes
Issuance of licensing decision (Agency Action) 05-29-2026 06-18-2026 --- Yes
In Progress
Milestone adjusted in response to NEPA milestone change., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 03-04-2024 03-04-2024 --- Yes
Acceptance review complete (Agency Action) 06-24-2024 06-24-2024 --- Yes
Issuance of licensing decision (Agency Action) 05-29-2026 06-23-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 03-04-2024 03-04-2024 --- Yes
Acceptance review complete (Agency Action) 06-24-2024 06-24-2024 --- Yes
Issuance of licensing decision (Agency Action) 05-29-2026 05-29-2026 --- No