Permitting Action Modification History
Modifications on 10/16/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 07-23-2027 | 07-23-2027 | --- | No |
| Scoping (Agency Action) | 08-23-2027 | 08-23-2027 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 07-14-2028 | 07-14-2028 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 07-14-2028 | 07-14-2028 | --- | No |