Permitting Action Modification History

Planned
BLM is not able to initiate consultation for Section 106 until review of cultural baseline studies submitted on 10/16/2026 concludes. The new target date for initiation of consultation is 12/14/2026., basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 10-31-2026 12-14-2026 No
Section 106 consultation concluded (Agency Action) 04-30-2027 04-30-2027 No
Planned
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 10-31-2026 10-31-2026 No
Section 106 consultation concluded (Agency Action) 04-30-2027 04-30-2027 No