Permitting Action Modification History

Planned
BLM requires additional time to review information submitted by the applicant on 10/16/2026. The determination to prepare an EA target date is now 12/14/2026., basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 10-31-2026 12-14-2026 No
Issuance of a Final EA (Agency Action) 04-30-2027 04-30-2027 No
EA Process Concluded (Agency Action) 04-30-2027 04-30-2027 No
Planned
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 10-31-2026 10-31-2026 No
Issuance of a Final EA (Agency Action) 04-30-2027 04-30-2027 No
EA Process Concluded (Agency Action) 04-30-2027 04-30-2027 No