Permitting Action Modification History
Modifications on 08/06/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 08-13-2027 | 11-13-2026 | No |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 11-12-2027 | 03-28-2027 | No |
| ESA Consultation Concludes (Agency Action) | 04-10-2028 | 04-29-2027 | No |
Modifications on 07/07/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 08-13-2027 | 11-13-2026 | No |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 11-12-2027 | 03-28-2027 | No |
| ESA Consultation Concludes (Agency Action) | 04-10-2028 | 04-29-2027 | No |
Modifications on 10/24/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 08-13-2027 | 08-13-2027 | No |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 11-12-2027 | 11-12-2027 | No |
| ESA Consultation Concludes (Agency Action) | 04-10-2028 | 04-10-2028 | No |