Permitting Action Modification History

Complete
Consultation concluded early, basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-11-2026 08-26-2026 Yes
Section 106 consultation concluded (Agency Action) 05-31-2028 09-17-2026 Yes
In Progress
Rawlins FO initiated the SHPO consultation 8/26/26.  The APE maps were received earlier than expected from the consultant WWC Engineers., basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-11-2026 08-26-2026 Yes
Section 106 consultation concluded (Agency Action) 05-31-2028 09-29-2026 No
Planned
The BLM provided the sponsor's contractor review comments and information, and the contractor responded that they will need until 8/24 to correct and update the Mine Plan of Operations.  The SHPO will need 30 days to complete review so that Section 106 milestone was moved also to provide for the time. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-11-2026 08-28-2026 No
Section 106 consultation concluded (Agency Action) 05-31-2028 09-29-2026 No
Planned
The NEPA is now anticipated to be an EA level review. The Section 106 consultation timeline has changed because of the project moving from EIS to EA. , basic_html
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-11-2026 08-11-2026 No
Section 106 consultation concluded (Agency Action) 05-31-2028 09-15-2026 No
Planned
N/A
Milestone Original Target Date Current Target Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-11-2026 08-11-2026 No
Section 106 consultation concluded (Agency Action) 05-31-2028 05-31-2028 No